Afcons Infrastructure Ltd. v. Cherian Varkey Construction Co. (P) Ltd. — (2010) 8 SCC 24
Vaidehi Sharma
Citation: (2010) 8 SCC 24
Petitioner: Afcons Infrastructure Ltd.
Respondent: Cherian Varkey Construction Co. (P) Ltd.
Date of Judgement: 26/07/2010
Bench: R.V. Raveendran and J.M. Panchal, JJ.
FACTS AND BACKGROUND OF THE CASE
A contractual arrangement between the parties was the source of the conflict. Afcons Infrastructure Ltd., the appellant, was hired by the Cochin Port Trust to carry out specific building projects, such as roads and bridges. Afterward, Afcons hired Cherian Varkey Construction Co. (the first respondent) to do part of the work. Cherian Varkey filed a lawsuit for Rs. 210,70,881 plus interest, alleging non-payment for the job completed under the subcontract. The subcontract lacked an arbitration clause. Cherian Varkey submitted an application under Section 89 of the CPC in March 2005, asking the trial court to determine parameters for a settlement and send the case to arbitration. Afcons disagreed, claiming that mutual consent was necessary for arbitration to continue.
Afcons appealed to the Kerala High Court after the trial court granted the application under Section 89. The High Court maintained the lower court's ruling, holding that a prior arbitration agreement was not necessary under Section 89. Afcons took the issue to the Supreme Court because they were not satisfied.
ISSUES INVOLVED
1. Whether the clause gives the court the authority to refer parties to a lawsuit to arbitration without both parties' assent come up? 2. Regarding the arguments made, two issues come up for discussion: a. How should a court carry out the implementation of Section 89 and Order 10 Rule 1A of the Code?
b. Does reference to arbitration under section 89 of the Code require the assent of all parties to the lawsuit? Does the ADR Process need to be mentioned?
3. Cases needing court protection, such as lawsuits for declaration of title against the government and claims against juveniles, gods, and people with mental disabilities.
ARGUMENTS FROM THE PETITIONERS SIDE
1. The appellants contended that a legitimate agreement between parties is necessary for arbitration by deLinition and in accordance with the Arbitration and Conciliation Act of 1996. They argued that this essential criterion is not and cannot be superseded by Section 89 CPC.
ARGUMENTS FROM THE RESPONDENTS SIDE
1. Unless the judge has a thorough discussion with both parties, the court will not be able to determine the conditions of the settlement. It is neither practical nor feasible for the court to determine the terms of settlement based only on the pleadings. Therefore, a major obstacle to courts applying section 89 of the Code is the necessity that the court create the terms of settlement. Therefore, by comparing "terms of settlement" to a "summary of disputes," this Court attenuated this ambiguity in Salem Bar (II), meaning that the court is simply needed to establish a "summary of disputes" rather than "terms of settlement." How should one understand section 89?
More to Read
Afcons Infrastructure Ltd. v. Cherian Varkey Construction Co. (P) Ltd. — (2010) 8 SCC 24
case briefs
Bharat Aluminium Co. v. Kaiser Aluminium Technical Services Inc. (BALCO) — (2012) 9 SCC 552
case briefs
ONGC LTD. V. SAW PIPES LTD, (2003) 5 SCC 705
case briefs
AMAZON.COM NV INVESTMENT HOLDINGS LLC V. FUTURE RETAIL LTD. & ORS.
case briefs
Mankastu Impex Private Limited vs Airvisual Limited
case briefs
Salem Advocate Bar Association, Tamil Nadu v. Union of India — (2005) 6 SCC 344
case briefs